The Aurora LNG Project is currently in the early stages of a thorough, independent environmental assessment process, led by the British Columbia Environmental Assessment Office (BCEAO).

Subject to obtaining an Environmental Assessment Certificate, regulatory permits and making a final investment decision, we anticipate beginning construction in 2020. At the end of its operational life, Aurora LNG would decommission the facility and reclaim the land according to regulatory requirements.

We will take a phased approach to construction:

  • Phase 1 (site preparation; construction of the materials offloading facility, camp, marine terminal; construction of trains 1 and 2)
  • Phase 2 (construction and commissioning of trains 3 and 4)
Project PhaseAnticipated Schedule
Phase 1 Construction 2020-2024
Phase 1 Commissioning and Start up 2025
Phase 2 Construction and Commissioning  Market driven
Operations 2026-2051+
Decommissioning 2052+, will start approximately 12 months
after the end of operations